Critical incident

University of Waterloo: Hyper-V VMs affected by a network power outage - Outage

Aug 20, 2026, 19:48 UTC
started
13:57 UTC
resolved September 4, 2026
14 days 18 h
duration

Affected: Virtual Infrastructure

Current status of University of Waterloo: Minor issues — live University of Waterloo status

Timeline

  1. Aug 20, 2026, 19:48 UTC
    investigating
    Hyper-V Dev environment was affected by a network equipment power outage, storage and VMs went offline. We have now recovered and restored VM state. Please let us know if there's any issue.
  2. Sep 4, 2026, 13:57 UTC
    resolved
    Root cause has been identified and resolved. Hyper-V Dev environment was affected by a network equipment power outage, storage and VMs went offline. We have now recovered and restored VM state. Please let us know if there's any issue.